NTPC Limited is establishing coal based Kudgi STPP of 3x800 MW generation project at village Kudgi, Bijapur District in the State of Karnataka. NTPC Limited has been granted LTA for 2392.49 MW as per the LTA application & the details of drawl of power is given below:

Karnataka Discoms 1196.24 MW
KSEB 119.18 MW
TANGEDCO 300.10 MW
AP Discoms 1196.24 MW

The Transmission System Strengthening was planned for the evacuation & supply of power from the Kudgi TPS to the beneficiaries of the generation project which include Kudgi TPS - Narendra (New) 400 kV 2 x D/C quad lines, Narendra (New) - Madhugiri 765 kV D/C line and Madhugiri - Bidadi 400 kV D/C (quad) line.

This transmission system strengthening shall facilitate immediate evacuation as well as supply of power to its beneficiaries with reliability & security. Beyond Madhugiri&Bidadi dispersal of power to the beneficiaries of the generation project shall be through existing/planned transmission network under Inter-State Transmission System.

Project Elements

1. Kudgi TPS - Narendra (New) 400 kV 2 x D/C Quad lines
2. Narendra (New) - Madhugiri 765 kV D/C line
3. Madhugiri - Bidadi 400 kV D/C (quad) line

Name of project specific SPV

Kudgi Transmission Limited

Name of the successful Bidder M/s L&T Infrastructure Development Projects Limited
Date of transfer of SPV to successful Bidder/Effective Date 30th August 2013
Scheduled COD of the Project 29th December 2015
Levelized Transmission tariff of successful Bidder Rs. 1795.8652 million per annum

Result

Result of financial bids

 

Our locations


Corporate Office

ECE House, 3rd Floor, Annexe - II,
28A, KG Marg, New Delhi - 110001

Registered Office

Core-4, Scope Complex7,

Lodhi Road,New Delhi – 110 003

Get in touch


Tel: 011-47964796

Fax: 011-47964747

Youtube Channel