Transmission System Strengthening in India System for Transfer Power from New HEPs in Bhutan
Punatsangchhu-I (1200MW), Punatsangchhu-II (990MW), Mangdechhu(720MW) and Wangchhu (570MW) Hydro Generation Projects in Bhutan are at various stages of development. Power from these generation projects would be transferred to India after meeting small local demand in Bhutan
Power from above generation projects is proposed to be brought to Alipurduarsub-station in West Bengal (India). Power transfer from Alipurduar onwards shall be done through + 800 kV, 6000MW Bishwanath Chariyal (Assam) – Alipurduar (West Bengal) – Agra (Uttar Pradesh) HVDC bipole link and Alipurduar – Siliguri & Kishanganj – Darbhanga400kV D/c (quad moose) lines.
Project Elements |
Transmission Lines: Alipurduar - Siliguri 400 kV D/C line (2nd) with Quad moose conductor Kishanganj - Darbhanga 400kV D/C line with Quad moose conductor 400 kV Bay Requirements 1. 400 kV line bays at Darbhanga: 2 nos. 2. 80 MVAR switchable line reactors (400 Ohm NGR) in each circuit at Darbhanga end of Kishanganj - Darbhanga 400kV D/C (quad) line |
Name of project specific SPV |
|
Name of the successful Bidder |
M/s Kalpataru power Transmission Limited |
Date of transfer of SPV to successful Bidder/Effective Date |
06.01.2016 |
Scheduled COD of the Project |
06.03.2019 |
Levelized Transmission tariff of successful Bidder |
1294.24 Millions |
Results |
|